top of page

Library Extension - Update. New Room Now Ready!

Work started on our extension on 29th August 2017 and we felt that we should try to keep you up-to-date about developments.

The photos show the external building work as it progresses, in reverse order of time, from the most recent to the oldest.

Here's the situation on 3rd January 2018

The interior of the main extension has now been completed - there are still some bits and pieces to be done outside - and it can be used for activities!

These three pictures show it looked on 3rd January - without chairs, tables, etc.

This picture was taken from the door into the extension from the main library

This picture was taken from the 'far end' of the library.

This picture was taken from the 'far end' of the extension, looking back towards the door to the main library.

Here's a first look at the inside of the main extension, taken on 20th December 2017.

This picture was taken on 20th December 2017, from the playing field at the rear of the library.

This picture was taken on 17th November 2017, from the playing field at the rear of the library.

This is a view of the main extension, taken from the rear of the library. (13th November 2017)

Here's a view of the main extension, taken from the playing field at the rear of the library, so that you can see the extension in context. (13th November 2017)

This is the smaller extension (to the left of the library when viewed from St Giles Avenue). Again, this picture was taken from the rear of the library.

This is a picture of the state of play at the front of the library, bordering St Giles Avenue. (13th November 2017)

Here's a picture of the main extension, taken on 2nd November.

Just for a change, here's a look at some of the internal work that's being going on (this picture also from 2nd November). Previously existing windows on the main extension side of the library have been bricked up and the walls are awaiting a final skimming of plaster and repainting. As you can see, we also have new radiators (the old, inefficient heating syatem having been replaced) but shelves holding part of our non-fiction collection have had to be removed (temporarily) from the walls. When work on the internal walls is finally complete, the job of returning the shelves and books will commence.

Here's three views from 25th October 2017

This picture shows the progress being made on the main extension.

This picture shows work going on on the second part of the extension work, to the left hand side of the library

This picture shows the (rather muddy) approach to the main extension works.

Here's three views from 25th October 2017

12th October 2017

Another view of progress, also on 12th October

12th October 2017

As you can possible make out from the photos, this part of the extension is to provide a new activities room, behind the existing one.

Here's the state of play as it was on 6th October

6th October 2017

This is what it looked like on 12th September

12th September 2017

This was the start of actual work on 30th August.

30th August 2017

Fence erected on 29th August.

29th August 2017


Featured Posts
Recent Posts
Archive
Search By Tags
No tags yet.
Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
bottom of page